Question: The data below is for a small ICT project whose time estimates are in weeks. Use it to answer questions that follow. Activity Optimistic Time

The data below is for a small ICT project whose time estimates are in weeks. Use it to answer questions that follow.

Activity

Optimistic Time

Most Likely Time

Pessimistic Time

1-2

1

1

7

1-3

1

4

7

1-4

2

2

8

2-5

1

1

1

3-5

2

5

14

4-6

2

5

8

5-6

3

6

15

  1. Find the expected time and variance for each activity.
  2. Draw the project Network diagram.
  3. Find the expected length and the critical path.

What is the probability that the project can be completed 4 weeks before or three weeks after the expected time?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!