Question: The data below is for a small ICT project whose time estimates are in weeks. Use it to answer questions that follow. Activity Optimistic Time
The data below is for a small ICT project whose time estimates are in weeks. Use it to answer questions that follow.
| Activity | Optimistic Time | Most Likely Time | Pessimistic Time |
| 1-2 | 1 | 1 | 7 |
| 1-3 | 1 | 4 | 7 |
| 1-4 | 2 | 2 | 8 |
| 2-5 | 1 | 1 | 1 |
| 3-5 | 2 | 5 | 14 |
| 4-6 | 2 | 5 | 8 |
| 5-6 | 3 | 6 | 15 |
- Find the expected time and variance for each activity.
- Draw the project Network diagram.
- Find the expected length and the critical path.
What is the probability that the project can be completed 4 weeks before or three weeks after the expected time?