Question 4 (20 marks)

A software project comprises the following activities, whose time estimates are given against each other as below:

Activity Estimated Duration (weeks)
- Optimistic Most Likely Pessimistic
1-2 3 6 15
1-3 2 5 14
1-4 6 12 30
2-5 2 5 8
2-6 5 11 17
3-6 3 6 15
4-7 3 9 27
5-7 1 4 7
6-7 4 19 28

  1. Find the critical path for the project. (10 marks)

[Answer and show workings here]

  1. Whatis the planned project duration? (10 marks)

[Answer here]

Question 5 (20 marks)

A potential five-year project has a projected net cash flow of $15,000 in each of Years 1 and 2 and $12,000 in Years 3-5.

The cost of the project, incurred in Year 0, is $50,000. The company's required rate of return is 10%.

[Answer here]

Year Amount ($) Discounter NPV
0 -50,000
1 15,000
2 15,000
3 12,000
4 12,000
5 12,000
Total

a) Fill in the columns headed 'Discounter' and 'NPV' in the table above.(10 marks)

[Show workings here]

b) Advise the company as to whether or not to proceed with the project. Give reasons for your answer.(10 marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!