Question: This section contains two calculation questions. Answer BOTH questions. Each question accounts for 20 marks. Total 40 marks for this section. You MUST show all
This section contains two calculation questions. Answer BOTH questions. Each question accounts for 20 marks. Total 40 marks for this section. You MUST show all calculations.
Question 4 (20 marks)
A software project comprises the following activities, whose time estimates are given against each other as below:
| Activity | Estimated Duration (weeks) | ||
| - | Optimistic | Most Likely | Pessimistic |
| 1-2 | 3 | 6 | 15 |
| 1-3 | 2 | 5 | 14 |
| 1-4 | 6 | 12 | 30 |
| 2-5 | 2 | 5 | 8 |
| 2-6 | 5 | 11 | 17 |
| 3-6 | 3 | 6 | 15 |
| 4-7 | 3 | 9 | 27 |
| 5-7 | 1 | 4 | 7 |
| 6-7 | 4 | 19 | 28 |
- Find the critical path for the project. (10 marks)
[Answer and show workings here]
- Whatis the planned project duration? (10 marks)
[Answer here]
Question 5 (20 marks)
A potential five-year project has a projected net cash flow of $15,000 in each of Years 1 and 2 and $12,000 in Years 3-5.
The cost of the project, incurred in Year 0, is $50,000. The company's required rate of return is 10%.
[Answer here]
| Year | Amount ($) | Discounter | NPV |
| 0 | -50,000 | ||
| 1 | 15,000 | ||
| 2 | 15,000 | ||
| 3 | 12,000 | ||
| 4 | 12,000 | ||
| 5 | 12,000 | ||
| Total |
a) Fill in the columns headed 'Discounter' and 'NPV' in the table above.(10 marks)
[Show workings here]
b) Advise the company as to whether or not to proceed with the project. Give reasons for your answer.(10 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts