Question: The data regarding a project is given below. Activity Predecessors Time in weeks Optimistic Most probable Pessimistic A - 3 3 3 B - 1
The data regarding a project is given below.
| Activity | Predecessors | Time in weeks | ||
| Optimistic | Most probable | Pessimistic | ||
| A | - | 3 | 3 | 3 |
| B | - | 1 | 4 | 7 |
| C | - | 6 | 7 | 8 |
| D | B | 3 | 5 | 7 |
| E | A | 3 | 6 | 9 |
| F | A | 6 | 9 | 12 |
| G | B | 4 | 6 | 8 |
| H | C,D | 2 | 4 | 6 |
| I | C,D | 3 | 5 | 7 |
| J | E | 2 | 3 | 4 |
| K | F,G,H | 5 | 8 | 11 |
| L | F,G,H | 3 | 5 | 7 |
| M | I | 4 | 6 | 8 |
| N | J,K | 3 | 5 | 7 |
- Draw a pert network.
- Find the expected duration and variance of the activity.
- Find the critical path and the expected project completion time.
- Develop an activity schedule.
- With how many weeks would you expect the project to be completed with 96% chance?