Question: The demand for subassembly S is 110 units in week 7 . Each unit of S requires 1 unit of T and 1 unit of
The demand for subassembly S is 110 units in week 7 . Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 2 units of V,1 unit of W, and 2 units of X Finally, each unit of U requires 2 units of Y and 2 units of Z One firm manufactures all items. It takes 2 weeks to make S,2 weeks to make T,2 weeks to make U,2 weeks to make V, 2 weeks to make W, 1 week to make X,2 weeks to make Y, and 2 weeks to make Z Click the icon to view the product structure and the time-phased product structure. In addition to 110 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6 . Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used)