Question: The direct and indirect costs for each duration (days) for a project are as shown in the tables below. Compute the direct, indirect, and


The direct and indirect costs for each duration (days) for a project are as shown in the tables below. Compute the direct, indirect, and total costs for crashing one day at a time from this project. What is the optimum cost-time schedule? The customer offers you $10 for every day you shorten the project from your original network Would you take in? If so for how many days? Include the incentive amount in your total cost calculations Activity Crash cost Maximum ID (Slope) Crash Time Normal time Normal cost A 80 2. 10 40 30 3. 8. 10 40 5. 80 50 11 50 100 4. 15 100 30 20 Total direct noImal costs $300 Tine units 27 26 Indirect costs $300 240 25 180 24 23 22 120 60 A 10 11 9. 15 Total direct cost: $300 Total indirect cost: $300 Total incentive Completion time: 27 Total cost: $600 The optimum cost-time schedule for the project is days at a cost of You should accept the offer for 1 day accept the offer for 2 days accept the offer for 3 days accept the offer for 4 or more days not accept the offer
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
Given Activity Normal Normal Allowable crashing weeks Crashing cost per week Duration Weeks ... View full answer
Get step-by-step solutions from verified subject matter experts