Question: If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60
If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every day you shorten the project from your original network. Would you take it? If so for how many days?
-1.png)
-2.png)
Crash Act. Maximum Normal Normal Cost Crash Time Time Cost (Slope) 80 10 40 10 30 3 40 80 D 50 2 11 50 100 4 15 100 30 1 $300 A D 10 11 Project duration 27 Total direct cost $300 15 B. 00
Step by Step Solution
3.40 Rating (166 Votes )
There are 3 Steps involved in it
With no incentive day 27 has total direct cost of 300 and total indirect cost of 300 for a total of ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1379-B-M-L-P-M(2688).docx
120 KBs Word File