Question: If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60

If the indirect costs for each duration are $300 for 27 days, $240 for 26 days, $180 for 25 days, $120 for 24 days, $60 for 23 days, and $50 for 22 days, compute the direct, indirect and total costs for each duration. What is the optimum cost-time schedule? The customer offers you $10 for every day you shorten the project from your original network. Would you take it? If so for how many days?

Crash Act. Maximum Normal Normal Cost Crash Time Time Cost (Slope) 80 10 40 10 30 3 40 80 D 50 2 11 50 100 4 15 100 30 1
A D 10 11 Project duration 27 Total direct cost $300 15 B. 00

Crash Act. Maximum Normal Normal Cost Crash Time Time Cost (Slope) 80 10 40 10 30 3 40 80 D 50 2 11 50 100 4 15 100 30 1 $300 A D 10 11 Project duration 27 Total direct cost $300 15 B. 00

Step by Step Solution

3.40 Rating (166 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

With no incentive day 27 has total direct cost of 300 and total indirect cost of 300 for a total of ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1379-B-M-L-P-M(2688).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!