Question: The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A

The duration and resource usage for each activity are showed in the table below.

The duration and resource usage for each activity are showed in the

Activity Predecessor Total Processing Time (days) # of painters required/day A --- 0.5 2 B A 1 2 C B 1 1 D B 1 2

How many painter-days are required for the whole project?

\begin{tabular}{|c|c|c|c|} \hline Activity & Predecessor & \begin{tabular}{l} Total \\ Processing \\ Time \\ (days) \end{tabular} & \begin{tabular}{l} \# of painters \\ required/day \end{tabular} \\ \hline A & --- & 0.5 & 2 \\ \hline B & A & 1 & 2 \\ \hline C & B & 1 & 1 \\ \hline D & B & 1 & 2 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!