Question: The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A
The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A --- 1 1 B --- 0.5 2 C A,B 1 1 D C 1 2 How many painter-days are required for the whole project