Question: The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A
The duration and resource usage for each activity are showed in the table below.
| Activity | Predecessor | Total Processing Time (days) | # of painters required/day |
| A | --- | 0.5 | 1 |
| B | --- | 1 | 1 |
| C | A,B | 1 | 1 |
| D | C | 1 | 1 |
Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day 1).
Answer Options:
In the morning of Day 2
The whole day of Day 1
In the morning of Day 1
The whole day of Day 2