Question: The duration and resource usage for each activity are showed in the table below. Activity Predecessor Total Processing Time (days) # of painters required/day A

The duration and resource usage for each activity are showed in the table below.

Activity

Predecessor

Total Processing Time (days)

# of painters required/day

A

---

0.5

1

B

---

1

1

C

A,B

1

1

D

C

1

1

Assume the maximum number of painters is 1. Level the resources by following the rule "Delay the activity with the most positive slack first". Please indicate the schedule of acitivity B after leveling recources (Suppose the project begins on day 1).

Answer Options:

In the morning of Day 2

The whole day of Day 1

In the morning of Day 1

The whole day of Day 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!