Question: The earliest start time rule a . compares the starting times of all activities for successors of an activity. b . compares the finish times
The earliest start time rule
a
compares the starting times of all activities for successors of an activity.
b
compares the finish times for all immediate predecessors of an activity.
c
determines when the project can begin.
d
determines when the project must begin.