Question: The earliest start time rule Select one: a. O b. O C. O d. Determines when the project can begin. Compares the starting times

The earliest start time rule Select one: a. O b. O C. O d. Determines when the project can begin. Compares the starting times for all activity for successors of an activity. Compares the finish times for all immediate predecessors of an activity. Determine when the project must begin.
Step by Step Solution
3.53 Rating (160 Votes )
There are 3 Steps involved in it
Answer C Compares the finish times for all I... View full answer