Question: The earliest start time rule a. determines when the project must begin. b. determines when the project can begin. c. compares the finish times for
The earliest start time rule
| a. | determines when the project must begin. | |
| b. | determines when the project can begin. | |
| c. | compares the finish times for all immediate predecessors of an activity. | |
| d. | compares the starting times of all activities for successors of an activity. |