Question: The Edwin Construction Company is planning a project to construct a flag memorial to World War II veterans in the town square. The Table below
The Edwin Construction Company is planning a project to construct a flag memorial to World War II veterans in the town square. The Table below is the plan for the project.
To assist you in answering the questions below, you will need to draw a network diagram of the project to construct a flag memorial to World War II veterans on a separate sheet of paper. You will not submit your network diagram with your exam. It is only to assist in answering the questions.
| Activity | Immediate Predecessor(s) | Time (Weeks) |
| A | --- | 4 |
| B | A | 6 |
| C | A | 9 |
| D | A | 6 |
| E | C, D | 6 |
| F | B, D | 8 |
| G | E, F | 9 |
answer to the question
Questions to answer:
1. What is/are the critial path(s)?
2. What is the project completion time?
3. What is the Early Start (ES) time for Activity C?
4. What is the Early Finish (EF) time for Activity E?
5. What is the Late Start (LS) for Activity D?
6. Identify one activity that has slack time?
Step by Step Solution
There are 3 Steps involved in it