Question: The estimated mean time for an activity with a most likely time ( m ) equal to 1 2 weeks, an optimistic time ( a

The estimated mean time for an activity with a most likely time (m) equal to 12 weeks, an optimistic time (a) equal to 9 weeks, and a pessimistic time (b) equal to 18 weeks is
12.75 weeks.
9.0 weeks.
13.0 weeks.
12.5 weeks.