QUESTION 19
The estimated mean time for an activity with a most likely time (m) equal to 11 days, the optimistic time (a) equal to 6 days, and the pessimistic time (b) equal to 18 days is
A.11 days.
B.11.67 days.
C.9.67 days.
D.11.33 days.