The expected activity time in PERT analysis is calculated as: Group of answer choices a. the weighted
Fantastic news! We've Found the answer you've been seeking!
Question:
The expected activity time in PERT analysis is calculated as:
Group of answer choices
a. the weighted average of a m and b with m weighted times as heavily as a and b
b. the sum of the a m and b divided by
c. the simple average of the a m and b
d. the sum of the a m and b