Question: The expected activity time in PERT analysis is calculated as: Group of answer choices a. the weighted average of a , m , and b
The expected activity time in PERT analysis is calculated as:
Group of answer choices
a. the weighted average of a m and b with m weighted times as heavily as a and b
b. the sum of the a m and b divided by
c. the simple average of the a m and b
d. the sum of the a m and b
Step by Step Solution
3.30 Rating (144 Votes )
There are 3 Steps involved in it
In PERT Program Evaluation and Review Technique analysis the expected ac... View full answer