Question: The expected monetary value using inside engineers to complete the design is _____(Enter your response as an integer.) The expected monetary value using an outside

The expected monetary value using inside

The expected monetary value using inside engineers to complete the design is _____(Enter your response as an integer.)

The expected monetary value using an outside engineering firm to complete the design is

$_______(Enter your response as an integer.)

The expected monetary value of conducting a joint design is

$ _______(Enter your response as an integer.)

What is the best decision based on an expected monetary value criterion? A. Internal Engineers B. External Engineering Firm C. Joint Design

Sox Engineering designs and constructs air conditioning and heating (HVAC) systems for hospitals and clinics. Currently the company's staff is overloaded with design work. There is a major design project due in 7 weeks. The penalty for completing the design late is $15,000 per week, since any delay will cause the facility to open later than anticipated, and cost the client significant revenue. If the company uses its inside engineers to complete the design, it will have to pay them overtime for all work. Sox has estimated that it will cost $11,000 per week (wages and overhead), including late weeks, to have company engineers complete the design. Sox is also considering having an outside engineering firm do the design. A bid of $82,000 has been received for the completed design. Yet another option for completing the design is to conduct a joint design by having a third engineering company complete all electromechanical components of the design at a cost of $60,000. Sox would then complete the rest of the design and control systems at an estimated cost of $30,000. Sox has estimated the following probabilities of completing the project within various time frames when using each of the three options. Those estimates are shown in the following table: On Time Three Weeks Late Option Internal Engineers External Engineers Joint Design 0.3 0.1 0.1 Probability of Completing the Design One Week Late Two Weeks Late 0.5 0.2 0.5 0.3 0.3 0.4 0.1 0.2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!