The field team sends an update to the project manager letting him know that there were 12
Fantastic news! We've Found the answer you've been seeking!
Question:
The field team sends an update to the project manager letting him know that there were 12 employees at the project site, there were no accidents this week and no issues to report, and that the team is tracking toward on-time completion of their work. The project manager adds this information in a box on a report. What would you call this data provided to the project managers report?