Question: The first method for determining _ _ _ _ assumes that the work to be performed on the remaining portion of the project or work

The first method for determining ____ assumes that the work to be performed on the remaining portion of the project or work package will be done at the same rate of efficiency as the work performed so far.
Question 14 options:
forecasted cost at completion
cumulative actual cost
cumulative earned value
cost performance index