Question: The first two questions involve the project below with 5 activities. Activity Length Predecessor J 7 - K 4 J L 4 K,M M 5
The first two questions involve the project below with 5 activities.
| Activity | Length | Predecessor |
| J | 7 | - |
| K | 4 | J |
| L | 4 | K,M |
| M | 5 | - |
| N | 5 | M |
1 Draw the network below.
2 How many starting activities are there?
a) 1
b) 2
c) 3
d) 4
e) 5