Question: The first two questions involve the project below with 5 activities. Activity Length Predecessor J 7 - K 4 J L 4 K,M M 5

The first two questions involve the project below with 5 activities.

Activity Length Predecessor
J 7 -
K 4 J
L 4 K,M
M 5 -
N 5 M

1 Draw the network below.

2 How many starting activities are there?

a) 1

b) 2

c) 3

d) 4

e) 5