Question: 7 . Short answer and multiple choice ( clearly show the correct answer ) . The first two questions involve the project below with 5

7. Short answer and multiple choice (clearly show the correct answer).
The first two questions involve the project below with 5 activities.
Activity Length Predecessor
A 7-
B 4-
C 4 A
D 5 A,B
E 5 C
7.1 Draw the network below.
7.2 How many ending activities are there?
a)1.
b)2.
c)3.
d)4.
The following two questions involve a service process that has a mean of 88 seconds with a standard deviation of 5 seconds, where the upper and lower specification limits for the process are 100 seconds and 76 seconds, respectively.
7.3 What is the process capability ratio for this process?
a)0.667
b)0.80
c)1.25
d)3.00
e)17.6
f) none of these.
7.4 Is this process capable of providing an acceptable level of quality (99.7% acceptable)?
a) yes.
b) no.
7.5 The purpose of a control charts is to identify when a process has
a) random variation.
b) non-random variation.
7.6 There are two options for producing a product, A and B. Option A has a higher fixed cost than Option B, but a lower variable cost. If the variable cost of Option A was increased, then the level of production that causes both options to have the same total cost would
a) increase.
b) decrease.
c) stay the same.
7.7 The project shown below includes 10 activities (represented by the circles) with precedence relations as shown by the arrows. Activity times are not shown. What is the fewest number of activities that could be in the critical path?
a)1.
b)2.
c)3.
d)4.
e) none of the above.
7.8Crashing a project is used to
a) lengthen the time to complete a project.
b) shorten the time to complete a project.
c) find the earliest start and latest start of a project.
d) find the latest start and latest finish of a project.
7.9 There is a 20% chance the outcome is a gain of $2000 and an 80% chance the outcome is a loss of $500. What is the expected value of the outcome?
a) $1500.
b) $800.
c) $500
d) $0
e) none of the above.
7.10 For a control chart, what percentage of points are expected to be between the upper and lower control limits?
a)50%.
b)90%.
c)96.7%
d)99.7%
e)99.99%
f) none of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!