Question: . The following diagram represents a manufacturing process, which consists of five production stages, A , B , C , D , and E .

. The following diagram represents a manufacturing process, which consists of five production stages, A, B, C, D, and E. Setup times and run times are given in Table 1.
TABLE 1
STAGE SETUP TIME PER LOT
(minutes) PROCESSING TIME PER UNIT (minutes)
A 303
B 451
C 202
D 205
E 102
Assume that after processing each lot a new setup is required and all setups are done when a lot arrives to a stage and the company has determined that lot size will be 20 units.
a. Identify the bottleneck stage
b. What is the cycle time?
c. What is the throughput time?
d. What is the work-in-process inventory?
e. Assume the company is operating three shifts of 8 hours. What is the daily capacity of the operation (at steady state)?
f. How much idle time does each stage have?
g. What will be the throughput time and work-in-process inventory if idle time at stages are used for setup?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!