Question: The following information is given for a particular part. Using a lead time of two weeks, complete the table. Assume that the supplier requires a

The following information is given for a particular part. Using a lead time of two weeks, complete the table. Assume that the supplier requires a fixed lot size of 500 units with On hand = 80 and SS = 0.

The following information is given for a

Week 1 Week 2 Week 4 Week 3 100 Week 5 300 400 50 80 Gross requirement Scheduled receipts Projected ending inventory Net requirement Planned order receipts Planned order releases