Question: The following information is given: Work Task Task Time (seconds) Task Predecessor(s) A 70 - B 60 A C 120 B D 60 - E
The following information is given:
| Work Task | Task Time (seconds) | Task Predecessor(s) |
| A | 70 | - |
| B | 60 | A |
| C | 120 | B |
| D | 60 | - |
| E | 240 | C, D |
| F | 100 | A |
| G | 190 | E, F |
Develop a solution for the following line-balancing problem, allowing a cycle time of 5 minutes.
-
a) Draw the precedence diagram for the set of tasks.
-
b) Calculate the theoretical minimum number of workstations.
-
c) Balance this line using the most following tasks heuristic.
-
d) What tasks are assigned to which stations?
-
e) Does the solution have the minimum number of stations? Explain.
-
f) How much idle time is there, summed over all workstations?
-
g) What is the efficiency of this line?