Question: The following information is provided about a training and development project. Activity Duration (weeks) Preceding Activities A 3 None B 5 None C 14 A
The following information is provided about a training and development project.
| Activity | Duration (weeks) | Preceding Activities |
| A | 3 | None |
| B | 5 | None |
| C | 14 | A |
| D | 5 | A |
| E | 4 | B |
| F | 7 | B |
| G | 8 | D, E |
| H | 5 | G, F |
(a) Draw the PDM/CPM diagram, complete with forward and backward pass information. Find the critical path.
[12 marks]
(b) Assume Activity A (hire trainers) took 5 weeks. Draw the PDM/CPM diagram again.[7 marks]
(c) From which activity would you suggest transferring resources, and to what activity, so that the original target training date may be maintained?[6 marks]
[Total 25 marks]
sir if you can draw the diagrams on a paper since its easy to understand . thank you