Question: The following information is provided for a particular project: table [ [ Activity , table [ [ Expected ] , [ duration ]

The following information is provided for a particular project:
\table[[Activity,\table[[Expected],[duration]],\table[[Crashing],[Potential]],\table[[Cost per week to],[crash.]]],[1-2,4,1,$5,000
 The following information is provided for a particular project: \table[[Activity,\table[[Expected],[duration]],\table[[Crashing],[Potential]],\table[[Cost per