Question: The following is for question #16: NORMAL ACTIVITY SLACK TIME M LOME CRASH NORMAL | CRASH TIME COST COST $ 310,000 $ 500,000 $ 200,000

The following is for question #16: NORMAL

The following is for question #16: NORMAL ACTIVITY SLACK TIME M LOME CRASH NORMAL | CRASH TIME COST COST $ 310,000 $ 500,000 $ 200,000 $ 320,000 IS 90,000 $ 90,000 $ 180,000 $ 250,000 $ 80,000 $ 120,000 $ 225,000 $ 450,000 $ 100,000 $ 150,000 $ 400,000 $ 400,000 0-W 10. If you needed to crash this project, which activity would be the best choice for the first crashing option to reduce the project by one week? A. Activity R B. Activity T C. Activity M D. Activity U E. Activity P