Question: The following is true about performing project critical path analysis EXCEPT: a . The critical path is the longest path through the network b .
The following is true about performing project critical path analysis EXCEPT:
a
The critical path is the longest path through the network
b
The critical path is the longest time in which the project can be completed
c
Any delay in critical path activities delays the project
d
Critical path activities have no slack time