Question: The following is true about performing project critical path analysis EXCEPT: a . The critical path is the longest path through the network b .

The following is true about performing project critical path analysis EXCEPT: a. The critical path is the longest path through the network b. The critical path is the longest time in which the project can be completed c. Any delay in critical path activities delays the project d. Critical path activities have no slack time