Question: The following list represents a project. Normal time Crash time Activity Normal cost (day) (days) Crash cost Predecessor A 8 $1,000 $1,600 B 10 $2,000

The following list represents a project. Normal
The following list represents a project. Normal time Crash time Activity Normal cost (day) (days) Crash cost Predecessor A 8 $1,000 $1,600 B 10 $2,000 $2,600 5 $500 $1,000 D $4,000 $4,200 AB E $3,000 $4,000 C.D Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? 67471 B; $200 C: $100 O E: $1000 D: $100