Question: The following represents a project that should be scheduled using CPM. What is the critical path? Immediate predecessor Activity A B D E F G

 The following represents a project that should be scheduled using CPM.

The following represents a project that should be scheduled using CPM. What is the critical path? Immediate predecessor Activity A B D E F G D A D B,C E, F Time In Weeks 4 5 4 11 7 9 5 a. A-B-D-F-G O b. A-B-D-C-E OC. A-C-D-E-G Od. A-B-F-D-G e. A-D-C-F-G