Question: The following represents a project that should be scheduled using CPM: Intermediate Times(Days) Activity Predecessors a m b A ----- 1 2 6 B -----
The following represents a project that should be scheduled using CPM:
| Intermediate | Times(Days) | |||
| Activity | Predecessors | a | m | b |
| A | ----- | 1 | 2 | 6 |
| B | ----- | 1 | 2 | 9 |
| C | A | 2 | 2 | 11 |
| D | A | 1 | 8 | 9 |
| E | B | 1 | 2 | 3 |
| F | C,D | 3 | 4 | 11 |
| G | D,E | 1 | 3 | 11 |
| H | F,G | 2 | 3 | 11 |
What is the critical path?
What is the expected project completion time? (Round your answer to 3 decimal places.)
Project completion time ????? days
What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)
Probability ???