Question: The following represents a project that should be scheduled using CPM: Intermediate Times(Days) Activity Predecessors a m b A ----- 1 2 6 B -----

The following represents a project that should be scheduled using CPM:

Intermediate Times(Days)
Activity Predecessors a m b
A ----- 1 2 6
B ----- 1 2 9
C A 2 2 11
D A 1 8 9
E B 1 2 3
F C,D 3 4 11
G D,E 1 3 11
H F,G 2 3 11

What is the critical path?

What is the expected project completion time? (Round your answer to 3 decimal places.)

Project completion time ????? days

What is the probability of completing this project within 19 days? (Do not round intermediate calculations. Round your answer to 4 decimal places.)

Probability ???

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!