Question: The following represents a project that should be scheduled using CPM: TIMES (DAYS) b ACTIVITY ABCDEFGH IMMEDIATE PREDECESSORS | AABCDF C,D D, E F,G b.
The following represents a project that should be scheduled using CPM: b. What is the critical path? A.D.G.H A-D.F.H B-E-G-H A.C.F.H c. What is the expected project completion time? Note: Do not round intermediote colculations. Round your onswer to 3 decimal ploces. d. What is the probability of completing this project within 22 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate colculations. Round Z volue to 2 decimal ploces and final onswer to 4 decimal places