Question: The following table represents a project that should be scheduled using CPM Activity Immediate Predecessors Activity Duration (Days) A 5 B A 3 C

The following table represents a project that should be scheduled using CPM

The following table represents a project that should be scheduled using CPM Activity Immediate Predecessors Activity Duration (Days) A 5 B A 3 C A S D B.C 3 E C 4 F D,E S The critical path is The project completion time is and its length is days. days. (No, or in critical path. Just write ABCD inste