Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES ( DAYS ) a m b A 1 2 3

The following represents a project that should be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS)
a m b
A 123
B 147
C A 2811
D A 159
E B 123
F C,D 147
G D,E 123
H F,G 233
b. What is the critical path?