Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 2 6 B 1

The following represents a project that should be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS)
a m b
A 1 2 6
B 1 2 9
C A 2 2 11
D A 1 8 9
E B 1 2 3
F C,D 3 4 11
G D,E 1 3 11
H F,G 2 3 11

What is the critical path?

A-D-F-H

A-D-G-H

A-C-F-H

B-E-G-H

What is the expected project completion time?

Note: Do not round intermediate calculations. Round your answer to 3 decimal places.

What is the probability of completing this project within 19 days?

Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.

Thank you! Having trouble with excel at the moment

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!