Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 1 4 B 4

The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 1 4 B 4 5 6 C A 3 7 11 D A 1 2 9 E B 1 6 8 F C,D 1 2 12 G D,E 2 3