Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES ( DAYS ) a m b A 1 4 7

The following represents a project that should be scheduled using CPM:
ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS)
a m b
A 147
B 1611
C A 267
D A 3213
E B 126
F C,D 159
G D,E 129
H F,G 369
b. What is the critical path?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!