Question: The following represents a project that should be scheduled using CPM: Use Appendix G . TIMES ( DAYS ) ACTIVITY IMMEDIATE PREDECESSORS a m b

The following represents a project that should be scheduled using CPM: Use Appendix G.
TIMES (DAYS)
ACTIVITY IMMEDIATE
PREDECESSORS a m b
A 147
B 3510
C A 258
D A 4611
E B 123
F C, D 357
G D, E 126
H F, G 256
b. What is the critical path?
multiple choice
B-E-G-H
A-D-G-H
A-D-F-H
A-C-F-H
c.
What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.)
Project completion time
days
d.
What is the probability of completing this project within 22 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
Probability
rev: 09_06_2013_QC_35007Calculate this and show work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!