Question: The following represents a project that should be scheduled using CPM: Use Appendix G . TIMES ( DAYS ) ACTIVITY IMMEDIATE PREDECESSORS a m b
The following represents a project that should be scheduled using CPM: Use Appendix G
TIMES DAYS
ACTIVITY IMMEDIATE
PREDECESSORS a m b
A
B
C A
D A
E B
F C D
G D E
H F G
b What is the critical path?
multiple choice
BEGH
ADGH
ADFH
ACFH
c
What is the expected project completion time? Do not round intermediate calculations. Round your answer to decimal places.
Project completion time
days
d
What is the probability of completing this project within days? Use Excel's NORMSDIST function to find the correct probability for your computed Zvalue. Do not round intermediate calculations. Round z value to decimal places and final answer to decimal places.
Probability
rev: QCCalculate this and show work.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock