Question: The following represents a project that should be scheduled using CPM: Use Appendix G. TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A 1 2
The following represents a project that should be scheduled using CPM: Use Appendix G. TIMES (DAYS) ACTIVITY IMMEDIATE PREDECESSORS a m b A 1 2 6 B 1 2 3 C A 2 5 11 D A 1 2 12 E B 1 2 3 F C, D 1 3 5 G D, E 1 3 11 H F, G 2 3 11 b. What is the critical path? multiple choice A-C-F-H A-D-F-H B-E-G-H A-D-G-H c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.) Probability