Question: The following represents a project that should be scheduled using CPM Immediate Time (days ) Activity Predecessors a m b ET 2 - 2 4
The following represents a project that should be scheduled using CPM
| Immediate | Time | (days | ) | ||||
| Activity | Predecessors | a | m | b | ET | 2 | |
| - | 2 | 4 | 6 | ||||
| B | - | 2 | 5 | 8 | |||
| C | A | 1 | 3 | 5 | |||
| D | A | 6 | 7 | 14 | |||
| E | B | 2 | 5 | 8 | |||
| F | C,D | 1 | 4 | 7 | |||
| G | D,E | 1 | 3 | 5 | |||
| H | F,G | 3 | 4 | 5 |
a. Complete the table
b. Draw the Network Diagram
| c. What is the critical path? |
| d. What is the expected project completion time?' |
| e. What is the probability of completing this project within 16 days? |