Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 2 3 B 1

The following represents a project that should be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS)
a m b
A 1 2 3
B 1 4 7
C A 2 8 11
D A 1 5 9
E B 1 2 3
F C,D 1 4 7
G D,E 1 2 3
H F,G 2 3 3

  1. What is the critical path?

    multiple choice
    • A-C-F-H

    • A-D-G-H

    • B-E-G-H

    • A-D-F-H

  2. What is the expected project completion time?

    Note: Do not round intermediate calculations. Round your answer to 3 decimal places.

  3. What is the probability of completing this project within 20 days?

    Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!