Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 4 7 B 1

The following represents a project that should be scheduled using CPM:

ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS)
a m b
A 1 4 7
B 1 6 11
C A 2 6 7
D A 3 2 13
E B 1 2 6
F C,D 1 5 9
G D,E 1 2 9
H F,G 3 6 9

  1. What is the critical path?

    multiple choice
    • B-E-G-H

    • A-C-F-H

    • A-D-F-H

    • A-D-G-H

  2. What is the expected project completion time?

    Note: Do not round intermediate calculations. Round your answer to 3 decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!