Question: The following represents a project that should be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSORS TIMES (DAYS) a m b A 1 4 7 B 1
The following represents a project that should be scheduled using CPM:
| ACTIVITY | IMMEDIATE PREDECESSORS | TIMES (DAYS) | ||
|---|---|---|---|---|
| a | m | b | ||
| A | 1 | 4 | 7 | |
| B | 1 | 6 | 11 | |
| C | A | 2 | 6 | 7 |
| D | A | 3 | 2 | 13 |
| E | B | 1 | 2 | 6 |
| F | C,D | 1 | 5 | 9 |
| G | D,E | 1 | 2 | 9 |
| H | F,G | 3 | 6 | 9 |
-
What is the critical path?
multiple choice-
B-E-G-H
-
A-C-F-H
-
A-D-F-H
-
A-D-G-H
-
-
What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
Step by Step Solution
There are 3 Steps involved in it