Question: The following Table 1 provides information for this question. Table 1 Activity Immediate Predecessor Time (day) ES EF LS LF A - 25 B -

The following Table 1 provides information for this question.

Table 1

Activity

Immediate

Predecessor

Time

(day)

ES

EF

LS

LF

A

-

25

B

-

60

C

B

30

D

A

75

E

A

30

F

C, D

20

G

E

35

H

E, F

50

I

H,G

40

  1. Construct the network diagram for this project.
  2. Complete ES, EF, LS, and LF
  3. When is the latest start time for activity F and G?
  4. What is the critical path?
  5. What is the completion time for this project? (There is no customer demand)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!