Question: The following Table 1 provides information for this question. Table 1 Activity Immediate Predecessor Time (day) ES EF LS LF A - 20 B -
The following Table 1 provides information for this question.
| Table 1 | ||||||
| Activity | Immediate Predecessor | Time (day) | ES | EF | LS | LF |
| A | - | 20 |
|
|
|
|
| B | - | 60 |
|
|
|
|
| C | B | 30 |
|
|
|
|
| D | A | 70 |
|
|
|
|
| E | A | 30 |
|
|
|
|
| F | C, D | 20 |
|
|
|
|
| G | E | 30 |
|
|
|
|
| H | E, F | 50 |
|
|
|
|
| I | H,G | 40 |
|
|
|
|
- Construct the network diagram for this project.
- Complete ES, EF, LS, and LF
- When is the latest start time for activity C and D?
- What is the critical path?
- What is the completion time for this project?