Question: The following Table 1 provides information for this question. Table 1 Activity Immediate Predecessor Time (day) ES EF LS LF A - 2 B -

The following Table 1 provides information for this question.

Table 1

Activity

Immediate

Predecessor

Time

(day)

ES

EF

LS

LF

A

-

2

B

-

6

C

B

3

D

A

7

E

A

3

F

C, D

2

G

E

3

H

E, F

5

I

H,G

4

  1. Construct the network diagram for this project.
  2. Complete ES, EF, LS, and LF
  3. When is the latest start time for activity C and D?
  4. What is the critical path?
  5. What is the completion time for this project?