Question: The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Click here foc the Exrel

The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Click here foc the Exrel Dota file a. If 43 unis of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan) o. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint You don't need to develop an MRP plan,) b. An order for the end item is scheduled to be shipped at the start of week 13. What is the latest week that the order can be started and sult be ready to ship on time? (Hint. You don't need to develop an MRP plan.)