Question: The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G - Item LT (wk) Amount on

The following table lists the components needed

The following table lists the components needed to assemble an end item, lead times, and quantities on hand. G - Item LT (wk) Amount on hand End 1 0 B 3 7 C 1 12 D 1 22 E 1 8 F 1 29 1 - H 1 0 5 End Item B (2) C D (3) E (2) F(3) G (2) E (2) H14) E (2) If 21 units of the end item are to be assembled, how many additional units of E are needed? Additional units