Question: The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item End B C D E F
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
| Item | End | B | C | D | E | F | G | H |
| LT (week) | 1 | 3 | 1 | 1 | 1 | 1 | 1 | 1 |
| Amount on hand | 0 | 7 | 12 | 22 | 8 | 29 | 5 | 0 |
a. If 21 units of the end item are to be assembled, how many additional units of E are needed? (Hint: You don't need to develop an MRP plan to determine this.)
b. An order for the end item is scheduled to be shipped at the start of week 15. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)
Step by Step Solution
3.46 Rating (156 Votes )
There are 3 Steps involved in it
Answer To answer these questions we can utilize the information provided in the table a To determine ... View full answer