Question: The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount

The following table lists the components needed to assemble an end item, the manufacturing or purchase lead times (in weeks) for typical lot sizes, amount on Ira nd, and the direct components of each item and, in brackets, the number of each component for each parent.
The following table lists the components needed to assemble an

a. Draw the product structure tree for the End item.
b. If 40 units of the end item are to be assembled, how many additional units of B are needed? (You don€™t need to develop the MRP tables.)
c. An order for 40 units of the end item is scheduled to be shipped at the start of week 8. What is the latest week that the components of the order can be started and the order still be ready to ship on time? (You don€™t need to develop the MRP tables.)

Item Lead Time Amount on Hand Direct Components End item 10 15 20 30 30 [2), C(1), K(3) BI2, J(3) G(2), B 2 H(4), B 2)

Step by Step Solution

3.29 Rating (175 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b C B2 L 2 x 40 B 2 70 L2 80 10 70 140 30 110 Total B 11050 20... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

686-B-M-L-O-M (5193).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!